News from Leo Walmsley for June 2019

  • Working on the footpath up to Boredale Hause

    06:34 03 June 2019
    By Ade Mills, Pete Entwistle, Leo Walmsley

    Since our last blog post we've been busily working alongside the South Lakes team at Boredale Hause.

    Last year we completed work on the bridleway that leads up to Boredale and now in the second year of the project we're working on the footpath that runs parallel to, and just below, the bridleway.

     Starting work midway up the footpath

     Completed section of path

    We started midway up the footpath with the South Lakes team working on a section of path further down the hill.

     Stone on site and ready to begin work

    Completed footpath after landscaping

    As usual each team member worked on approximately a ten metre stretch and when completed leapfrogged over the person above them to advance further up the path.

     Starting work on another section

    Completed path

    The lower sections of the footpath were surprisingly easy digging for a change so we advanced fairly quickly.

     Work begins on a new section

     Getting further up the path

     Newly landscaped path

    As we got higher up the path we started to hit more bedrock, rubble and solid ground which has hindered progress a little but we're still making good headway. We're hoping that in two or three weeks we'll have the rest of the footpath completed and landscaped.

     Pile of rock ready to be dug in

     Advancing up the path

    Another completed section of footpath

    We've had a fair amount of dry weather since starting work in early April so a lot of the turfs are a little parched and the grass seed is taking it's time to grow but the recent rain we've had should hopefully help remedy things.